PRESS RELEASE
12 May 2016 | |
Consultation of the EDF Central Works Council (Comité Central d'Entreprise) on the Hinkley Point C project
Since the signing on October 21, 2015 of the Strategic Investment Agreement between EDF and China General Nuclear Power Corporation (CGN), which defined the principal terms of their partnership for the construction and operation of two 1600 MW EPR reactors at Hinkley Point C (HPC), discussions have continued which have led to the successful finalisation of contract documents in their stable form. Implementation of the arrangements with CGN was authorised respectively by the European and Chinese merger control authorities on March 10 and April 6 2016. The contracts with the British authorities [1] , which will come into effect when a final investment decision is made, are also in final form and ready to be signed, as are contracts with the main suppliers, notably Areva and GE/Alstom.
Before asking the EDF Board to consider a final investment decision, the Chairman and CEO of EDF wished to consult the Central Works Committee (CCE) in order to strengthen the social dialogue on this project of particular importance to EDF. The process of information and consultation was engaged upon on May 2 2016 and started by an information meeting with the CCE which took place on May 9 2016.
The consultation with the CCE covers the terms of the partnership with CGN for the HPC project for which the main terms are set out below.
The Hinkley Point C project
The two EPR reactors at Hinkley Point C in the southwest of England would provide around 7% of the UK's electricity needs. The schedule anticipates a 115 month construction period after the final investment decision until commissioning of the first reactor.
The Hinkley Point C project is ready to be launched:
The industrial and strategic partnership with CGN
The construction of new nuclear reactors in the UK is based on the longstanding strategic business partnership with CGN (Daya Bay, Ling Ao, Taishan). The new agreements would be based on three pillars:
In addition, EDF and CGN would enter into an Industrial Cooperation Protocol offering additional development opportunities for EDF, CGN and the French and Chinese supply chains in compliance with competition law.
The Contract for Difference (CfD)
Hinkley Point C would benefit from a secure revenue stream thanks to the CfD, which is a private law contract negotiated with the British Government.
The main features of the CfD are:
The terms of the HPC CfD were approved by the European Commission under the state aid rules on October 8, 2014.
Financing of the HPC project
Financing requirements until commissioning are estimated at £18bn in nominal terms [2] of which £2.4bn in development costs have been spent to date. The investment would be equity financed by each partner, at least in a first phase, with EDF Group's share amounting to £12bn and CGN's share being £6bn. The partners' equity commitment includes a contingency margin and could reach a total of £13.8bn for the EDF Group and £6.9bn to CGN. CGN would pay to EDF for the acquisition of its shares in the project a premium on top of its share of the development costs already expensed.
EDF would commit to provide CGN limited financial guarantees, particularly in the case of cost overruns delays to the project schedule, or in the event of a challenge to the CfD by European authorities
The projected rate of return (IRR) is estimated at around 9%, over the entire project duration. The sensitivity of the IRR is approximately 20 basis points for a six month delay.
For accounting purposes the project company would be consolidated into the EDF Group balance sheet.
Hinkley Point C is also eligible for the British Government infrastructure guarantee programme, a decision which was also approved by the European Commission in October 2014. An initial amount of £2bn could be made available at the time a final investment decision is taken.
The Sizewell C project (SZC)
This project provides the opportunity to develop two EPRs using the same technology used for HPC at Sizewell in the east of England. It would build on the experience gained during the development and construction of HPC.
The Bradwell B project (BRB) and the Generic Design Assessment (GDA) joint venture
This is the third part of the agreement with CGN. The Bradwell project in the east of England would be led by CGN using UK HPR 1000 technology subject to its approval by the safety authority. A joint venture would be created between EDF (33.5%) and CGN (66.5%), in order to obtain design approval (GDA) for the Chinese technology from the British safety authority.
The share of EDF in the development costs of the SZC and BRB/GDA projects is estimated at a maximum of around £600m phased over around five years.
[1] Nominal costs or current costs refer to the costs expressed in terms of their value when they are spent. They include the cost of inflation each year.
[2] The Contract for Difference, Secretary of State Investor Agreement, the IPA Guarantee, the Funded Decommissioning Programme and the Waste Transfer Contracts
A key player in energy transition, the EDF Group is an integrated electricity company, active in all areas of the business: generation, transmission, distribution, energy supply and trading, energy services. A global leader in low-carbon energies, the Group has developed a diversified generation mix based on nuclear power, hydropower, new renewable energies and thermal energy. The Group is involved in supplying energy and services to approximately 37.8 million customers, of which 28.3 million in France. The Group generated consolidated sales of €72.9 billion in 2014, of which 45.2% outside of France. EDF is listed on the Paris Stock Exchange.
Only print this message if you really need to
EDF SA 22-30, avenue de Wagram 75382 Paris cedex 08 Capital de 930 004 234 euros 552 081 317 R.C.S. Paris www.edf.fr |
CONTACTS
Press office: +33 1 40 42 44 19 Analysts and investors: +33 1 40 42 40 38 |